To carry out the mandate of the Central Interstate LLRW Compact by providing for and encouraging the safe and economical management of LLRW within the five-state Compact region;
To provide a framework for a cooperative effort to promote the health, safety, and welfare of the citizens and the environment of the Compact region;
To select the necessary regional facilities to accept compatible wastes generated in and from party states, and meeting the requirements of the Compact, giving each party state the right to have the wastes generated within its borders properly managed at such regional facilities;
To take whatever action is necessary
to encourage the reduction of waste generated within the Compact region;
and to faithfully and diligently perform its duties and powers as are granted
by the Compact.
Status of Commission Funds & KPMG Audit
The Commission’s developer, US Ecology, Inc., (USE) submitted a license application for a low-level radioactive waste disposal facility near the Village of Butte in Boyd County in July 1990. The application was submitted to the Nebraska Department of Environmental Control (now known as Environmental Quality and referenced as NDEQ) and the Nebraska Department of Health (now known as Health and Human Services and referenced as NDHHS).
The State of Nebraska deemed the application complete for technical review in December 1991. After several years of review, in May 1995, US Ecology submitted to the State its responses to the fourth and final round of the state’s technical comments.
In June 1995, US Ecology submitted its eighth revision to the Safety Analysis Report (SAR). On July 26, 1995, the LLRW Program indicated that it would take approximately one year to conduct its final review activities and confirmed that no more technical information would be accepted from the applicant unless the reviewers requested it. State evaluations and future decisions are to be based on this final product.
During 1995 and early 1996, the State did not issue a licensing public review schedule or commit to a binding licensing review schedule. Compact law, as well as individual laws in four of the five member states (Kansas law will be in force upon issuance of the license or permit to operate the disposal facility), charges the Commission to "require the Host State to process all applications for permits and licenses required for the development and operation of any regional facility or facilities within a reasonable period from the time that a completed application is submitted."
The Facility Review Committee for the project drafted a technical review schedule that was in compliance with the respective federal and state laws and regulations. This draft schedule was adopted by the Commissioners at their January 18, 1996, Mid-Year Meeting. At the Spring Quarterly Meeting on March 27, 1996, the Commissioners voted to reaffirm their schedule. At the Annual Meeting of the Commission on June 26, 1996, the Commissioners rescinded the Commission’s technical review schedule and unanimously approved setting a Special Commission Meeting on August 27, 1996, for the purpose of " . . . developing and determining a reasonable schedule for the completion of the processing of the pending application for a license for the Compact’s regional low-level radioactive waste disposal facility."
At public information meetings conducted by the NDEQ and the NDHHS on August 19 and 21, 1996, the state released information which called for the issuance of a Draft Safety Evaluation Report (DSER) and a Draft Environmental Impact Assessment (DEIA) in October 1997. This information was provided to the Commission along with other materials and comments received by the Commission when the Commission conducted its special meeting on August 27, 1996.
At the September 30, 1996, meeting, the Commissioners approved a motion that established a time frame between December 14, 1996, and January 14, 1997, as the scheduled date for receipt of the DSER and DEIA and a draft license decision from the LLRW Program. They also approved a motion that there be a single consolidated comprehensive public comment period and public hearing process on the draft documents and draft license decision.
On November 27, 1996, the State of Nebraska filed suit against the Commission regarding state compliance with the Commission’s two motions.
In October 1997, the State released their Draft Safety Evaluation Report and the Draft Environmental Impact Analysis . Of the 152 evaluation areas, the reviewers found US Ecology’s application and technical materials acceptable in 123 cases and unacceptable in only 29 instances. In the area of safety assessment, the state conducted their own Independent Performance Assessment for which the results indicated annual doses less than the regulatory limits. The state additionally indicated in the draft evaluation documents that the proposed facility would result in impacts to several environmental resources. However, the state’s draft environmental impact analysis indicated all potential adverse environmental impacts can be mitigated except for sociocultural impacts. The draft documents indicated that these impacts are expected to decline during the period of facility operation, assuming the facility operates without radiological accidents. The draft license decision was not released with the draft evaluation documents.
The release of the draft evaluation documents started the 90-day public comment period ending with a public hearing on the evaluation documents. The public hearings were held in early February 1998, in Naper, Nebraska and in Butte, Nebraska (the host community).
The interested public and the Commission’s developer participated in the public comment period and the public hearing. US Ecology said the state’s finding of 29 unacceptable areas provided clear guidance for future US Ecology work on fully resolving all regulatory concerns for the successful licensing of the llrw disposal facility. The 123 acceptable findings were also reviewed by US Ecology to confirm their technical sufficiency.US Ecology continued to conduct environmental sampling and monitoring in anticipation of the release of the state reviewer’s responses to the public comments they received and materials and testimony received during the February public hearing.
On August 6, 1998, Nebraska regulators announced in a press conference their "Intent toDeny" US Ecology’s license application to construct, operate, and close a LLRW disposalfacility in Butte, Nebraska. Public hearings were held in Naper, Nebraska November 9and 10, 1998 and in Butte, Nebraska, November 11 and 12, 1998.
December 21, 1998, NDEQ and NDHHS regulators denied US Ecology’s license application.The decision to deny the application cited six objections. All environmental monitoring activities at the Butte, Nebraska site ceased as of December 31, 1998.
After the issuance of the denial decision and also in December 1999, three of the four major waste generators of the Region filed a civil rights lawsuit against the State of Nebraska and its agents. The major generators named the Central Interstate Low-Level Radioactive Waste Commission as a defendant as well. They claimed injury due to the “bad faith” review by the State’s regulators.
On August 6, 1998, Nebraska regulators announced in a press conference their "Intent to Deny" US Ecology’s license application to construct, operate, and close a LLRW disposal facility in Butte, Nebraska. Public hearings were held in Naper, Nebraska November 9 and 10, 1998 and in Butte, Nebraska, November 11 and 12, 1998.
December 21, 1998, NDEQ and NDHHS regulators denied US Ecology’s license application. The decision to deny the application cited six objections. All environmental monitoring activities at the Butte, Nebraska site ceased as of December 31, 1998.
After the issuance of the denial decision and also in December 1998, three of the four major waste generators of the Region filed a civil rights lawsuit against the State of Nebraska and its agents. The major generators named the Central Interstate Low-Level Radioactive Waste Commission as a defendant as well. They claimed injury due to the "bad faith" review by the State's regulators.
At the Commission’s Mid-Year meeting January 13 and 27, 1999, various actions were taken in response to the denial decision by Nebraska regulators. Those actions included the initiation of cost-cutting measures and instruction of the Commission’s legal counsel and US Ecology to request a contested case hearing challenging the licensing decision.
On January 15, 1999, US Ecology filed petitions with the regulatory agencies seeking a contested case hearing to challenge the license decision. On January 19, 1999, counsel for the Commission filed petitions to intervene in the requested contested case hearings.
US Ecology Lincoln and Butte, Nebraska offices were closed March 31, 1999. Two of US Ecology’s staff members were available through the end of April to finalize project suspension arrangements.
In April 1999, in U.S. District Court Judge Richard Kopf granted a preliminary injunction barring Nebraska from spending any additional money paid by waste generators in the Central Interstate Compact on license review activities.
In May 1999, Nebraska’s legislature
passed LB530. Governor Mike Johanns signed the Bill withdrawing Nebraska
from the Central Interstate Compact effective August 27, 1999. Commissioners
voted at the June 1999 Annual Meeting to direct outside legal counsel to
research the ramifications of Nebraska's withdrawal.
Commissioners held a Special
Meeting to comply with the Commission's Rule 23, giving Nebraska an opportunity
to explain their decision to withdraw from the Compact, on September 22,
1999.
Background
On May 6, 1999, the Nebraska
Legislature adopted Legislative Bill 530 withdrawing Nebraska from the
Central Interstate Low-Level Radioactive Waste Compact
Commission. The Nebraska
Governor signed the Bill into law.
At the June 9, 1999 Annual
Meeting, Commissioners requested outside counsel to study issues relating
to Nebraska’s withdrawal from the Compact. Pursuant to the
Commission’s Rule 23, Governor
Johanns notified Chairman Henry and the other party states’ governors,
that the statute withdrawing Nebraska from the Compact became effective
August 28, 1999.
Rule 23 of the Central Interstate
LLRW Commission relates to the withdrawal of a compact member state or
the revocation of membership by the Commission. The
purpose of the Rule is to
specify the process by which a member state can withdraw from the Compact
and the penalties the Commission may enforce on the withdrawing state.
The Rule also instructs that upon receiving notice of the party state’s
withdrawal the Commission Chairman shall within 30 days convene a special
meeting of the Commission. The withdrawing state shall be notified
of this special meeting and shall have the opportunity to explain its decision
to withdraw.
On September 7, 1999 Commission Chairman Michael Henry responded to the Governor’s letter, acknowledging the receipt of the withdrawal notice and invited the State of Nebraska to attend the Special Meeting pursuant to Rule 23. The Chairman assured the Governor that it was not the purpose of Rule 23 to “consider, approve, or reject a state’s voluntary withdrawal from the Compact,” but rather “to consider whether at the time of withdrawal Nebraska has left unfulfilled or breached its duties prescribed under the Compact.”
In a letter dated September
17, 1999 Assistant Attorney General for the State of Nebraska and Special
Assistant Attorney for the State of Nebraska responded to
Chairman Henry’s letter
of invitation. The letter advised the Chairman that they would present
documents that included Legislative Bill 530, a copy of Governor’s notice
of withdrawal, and copies of the letters sent by Governor Johanns
to each of the party state governors. The letter stated that: “The tendered
documentation explains the State’s action and shows that Nebraska has fully
satisfied its Compact obligations regarding withdrawal. No further
explanation is necessary, and no sanctions for withdrawal are in order.”
Meeting
The Commission convened a Special Meeting to comply with the Commission’s Rule 23 on September 22, 1999. The meeting commenced with general business being conducted with the approval of export applications, the annual audit for 1998-1999, prepared by KPMG, LLP was received and the Chairman reported on his meeting with the South Carolina Compact Delegation and indicated that “we are not in the running.”
Representatives for the State of Nebraska and the Governor’s office were in attendance and made a brief statement while presenting a certified copy of Legislative Bill 530, withdrawing the State of Nebraska from the Central Interstate Compact and copies of the letters sent by Governor Johanns to the governors of each compact state and letters from Governor Johanns to Chairman Henry.
The Commission’s outside
legal counsel presented options on how to proceed according to Commission’s
Rule 23. Counsel repeated the State’s claim to “substantial
evidence” that it “has not
failed to comply with the terms of the Compact or to fulfill its obligations,”
and made the recommendation for the Commissioners to require Nebraska to
furnish the documents proving it innocent of the bad faith allegations.
The Commission’s decision was to request the documents. The meeting was
recessed with a future date to be determined by the Chairman.
The Central Interstate
LLRW Commission’s Mid-Year meeting was held in New Orleans, Louisiana on
January 12, 2000. The Commission voted to approve export applications,
meeting minutes, reports, US Ecology Year 2000 Funding Request, and the
Financial Consultant’s contract.
A panel of three sat before
the Commission as required by § 5.04 US Ecology Contract Review of
Options and Alternatives. The panel consisted of representatives
of the utilities, US Ecology, and the Commission. Discussion was
centered around the possible closing of the Barnwell, SC disposal facility
and the application for a Class B/C license by Envirocare of Utah.
Also discussed was the effects the closing might have on the minor generators
of the Central Interstate Compact.
A special meeting was
held via telephone in the Commission’s Lincoln, Nebraska office on April
12, 2000. Items taken action on were the approval of export applications
and budgetary line-item adjustments to fiscal year 1999-2000 Administrative
Budget to accomodate increased legal fees.
The export fee schedule for
fiscal year 2000-2001 was approved with a $6,000 increase to the utility
/ major generator category. The Commissioners approved the
Administrative Budget for
fiscal year 2000-2001 with an anticipated increase to legal fees.
The Commissioners voted to have prepared the necessary documentation to propose the return of the Major Generators’ contribution to the securement of the $1 million Guaranty Fund required by the Settlement Agreement of 1996.
The retiring Oklahoma Commissioner, H. A. Caves, was presented with a plaque of gratitude for his years of faithful service to the Commission by Chairman Henry.
Louisiana Commissioner, Michael
E. Henry, was elected for a second term to act as Chairman for fiscal year
2000-2001. The Mid-Year meeting was tentatively scheduled for January
24, 2001, in Oklahoma City, Oklahoma.
A special teleconference
meeting of the Commission was held on June 28, 2000. Export applications
were submitted by 16 generators for approval. The Commission approved
the applications for fiscal year 2000-2001.
The Commission voted to reimburse the contributing major generators $300,000 of the $400,000 used to secure the Rebate Settlement Guaranty Fund created under paragraph 10 of the rebate case settlement agreement dated June 20, 1996. The Commission replaced the returned money with rebate funds to maintain the $1 million Guaranty Fund.
The FRC held a teleconference meeting on November 18, 1998. Committee received US Ecology’s Developers Report and the Action Items Status Update report. It was decided to postpone US Ecology’s 1999 Annual Work Plan until possibly January 1999. Due to the Intent to Deny decision, US Ecology was directed to work under the 1998 Annual Work Plan. US Ecology planned to meet with the major generators to discuss trimming some budget items. US Ecology presented a revised funding request for the fourth quarter and approval was held over until the next FRC meeting.
Due to the events occurring during this reporting period, November 18, 1998, was the last FRC meeting.
U.S. District Judge Richard G. Kopf signed an order December 17, 1999 authorizing a computer expert to retrieve missing e-mail files from the State of Nebraska’s computers. Judge Kopf also directed the State to prepare a report on how much potential evidence was lost in the bad faith lawsuit. The report completed by the State’s Attorney General’s office reported that the deletion was inadvertent and the loss appears to be minimal. Apparently, the error occurred during the change of administration in the governor’s office. The new administration was not notified of the extension on Judge Kopf’s previous order to preserve the records.
Judge Kopf appointed a special master to supervise the attempt to recover the missing e-mail.
The Nebraska Department of
Environmental Quality requested an additional $4 millon for its low-level
radioactive waste program for the year 2000. According to a
deficit request submitted
to Governor Johanns, most of the cost is associated with legal expenses.
The request resulted from U.S. District Judge Richard Kopf’s April 16,
1999 order that the state cannot collect money from public utilities while
the lawsuit is pending.
Legislative Bill 606,
extending through calendar year 1999, was introduced and advanced to the
general file of the Unicameral during the 1999 session. This Bill
remains on general
file and was not acted upon during the 2000 session.
The law, authorized and established
in 1987, ensures continued funding assistance for the Village of Bute (Host
Community) and a number of other local political subdivisions in Boyd County
which are impacted by the selection of the proposed disposal facility site.
Annual amounts of $75,000 each are to be provided by the states of Arkansas,
Kansas, Oklahoma, and Louisiana upon annual passage of the statue by the
Nebraska Legislature.
In September 1998, the
Executive Board of the Nebraska Legislative Council contracted Arent, Fox,
Kintner, Plotkin & Kahn, a Washington, DC law firm to perform an analysis
of the legal consequences of withdrawing from the Central Interstate Low-Level
Radioactive Waste Compact. An executive summary of the report was
publicly issued in January 1999 and indicated that Nebraska is responsible
for the $25,000 annual membership dues over the five-year withdrawal period
totaling $125,000.
After Governor Johanns signed
the legislation withdrawing the state, Nebraska’s Attorney General requested
the report to assist him in defending the state against any
potential lawsuits filed
due to the withdrawal from the Compact. Nebraska lawmakers debated
if providing the Attorney Generals office with the report would constitute
a waiver of the attorney-client privilege consequently making the report
a public document. On July 20, 1999, the Nebraska Legislature’s Executive
Board voted unanimously to provide the state’s Attorney General with the
report.
The Nebraska Department of Environmental Quality stated in their annual report to the Nebraska Legislature that since March 8, 1999, the NDEQ has paid the LLW Program expenses from the State’s general fund budget.
The NDEQ report, submitted
December 1, 1999, also reported that since the Local Monitoring Committee
funds were not collected from the developer, the 1999
Legislature appropriated
$50,000 of State general funds for the Committee’s expenses.
The Low-Level Radioactive
Waste Program (LLRW Program) was created to administer the Nebraska Department
of Environmental Quality’s (NDEQ) responsibilities as outlined in Nebraska
State Statute through the Low-Level Radioactive Waste Disposal Act.
The LLRW Program is a cooperative effort on behalf of NDEQ and the Nebraska
Department of Health and Human Services (NDHHS).
The Commissioners voted to approve funding for the continued maintenance of the Boyd County disposal facility site as requested by US Ecology to maintain site viability for future disposal facility development purposes. The Commission-approved budget provided for costs associated with the maintenance of the proposed facility site including such required activities as mowing, noxious weed control, site surveillance, property tax payments, and other items.
US Ecology’s representative
reported at the Annual Meeting that an inspection of the property had been
performed. The native grasses planted three years ago have
germinated The water that
has delayed the completion of the removal of the remaining two monitoring
wells has subsided. It is anticipated that with the dry weather, water
levels will continue to subside. US Ecology will continue to monitor
and report to the Commission any changes in the site status.
Another item reported on was the expiring wetland mitigation permit issued by the Corps of Engineers. A two-year extension was granted bringing the expiration date of the permit to December 2001.
US Ecology vs. State of Nebraska
(whether mitigating a wetland less than one acre in size constituted the
start of facility construction) was settled by the Supreme Court of Nebraska
in October, 1999. The court reversed a lower court's judgment in favor
of US Ecology and remanded the case with directions to dismiss. According
to the state supreme court, "[d]declaratory judgment cannot be used to
decide the legal effect of a state of facts which are future, contingent,
or uncertain." In the context of this particular case this means
that US Ecology would have had to actually fill the wetland and then see
whether or not the state would actually implement it’s stated threat to
deny the license on grounds of starting construction without a license.
US Ecology will continue to monitor developments on both the state and
federal levels
for any actions which could
affect the viability / integrity of the license application. This
includes potential state regulatory changes and federal actions which could
affect the status of the Low-Level Radioactive Waste Policy Act.
On September 23, 1999,
the U.S. General Accounting Office (GAO) released the report “Low-Level
Radioactive Wastes: States Are Not Developing Disposal Facilities”
prepared at the request of Senator Frank Murkowski (R-AK) who chairs the
Senate Committee on Energy and Natural Resources. In a chapter entitled
“Future Access Concerns Raise Questions About the Appropriate Approach
for Managing Wastes”, three options available to Congress are analyzed.
The three options are retaining the compact approach, repealing the compact
legislation, and making DOE responsible for disposal of commercial low-level
radioactive waste.
Reasons for not developing
disposal facilities sited in the report were public and political opposition,
declining waste volumes, high cost of disposal facilities, expressed interest
in long-term storage, and most waste generators currently have access to
a facility.
The Commission’s office
did not conduct a formal waste survey for the 1999-2000 reporting period.
However, with the possible closing of the Barnwell, S.C. disposal
facility an informal telephone
poll was taken of 15 minor generators for the purose of determing how the
closing of Barnwell might affect their facilty.
The generators were chosen based on their applications for export permits during fiscal year 1999 and / fiscal year 2000. The majority of generators estimated that they would be able to store waste for six months to three years. Two generators indicated they would be in trouble immediately because they have no storage and no plans to build storage. One generator said that animal carcasses would be an immediate problem due to regulations on incineration versus cremation. Three indicated they have built on-site storage and could safely store waste for longer than three years. One generator could store waste in the laboratory for approximately one year. One generator uses cargo containers as a method of providing storage.
Many explained their efforts
in trying new technologies and minimization strategies that include the
purchase of industrial compactors and incinerators to reduce volume.
One university is considering charging their researchers a fee for disposal
/ storage of waste to encourage minimization.
Disposal information
included in this report is from the National Low-Level Waste Management
Program’s web site. The site provides both national and state-specific
disposal data of low-level
radioactive waste. (http://www.inel.gov/national/national.html) Data
is also presented on the MIMS system at http://mims.inel.gov
through the current month.
|
|
|
|
| Arkansas |
1574.11
|
5.18
|
| Kansas |
691.33
|
918.33
|
| Louisiana |
3893.18
|
1340.68
|
| Nebraska |
1484.45
|
108.14
|
| Oklahoma |
494.34
|
.33
|
| 1999/2000 Totals |
8137.41
|
2372.66
|
During this reporting period, the generators of low-level radioactive waste in the Central Interstate Region have had access to out-of-region disposal facilities located at Barnwell, South Carolina and Clive, Utah.
The Commission approved 26
export applications for this reporting period.
On June 9, 2000, GTS
Duratek, Inc. announced the completion of the aquistion of Chem-Nuclear
Systems. South Carolina joins the Northeast LLRW Compact to form the Atlantic
LLRW Compact to become effective July 1, 2000. This union will close
the Barnwell facility to non- Atlantic Compact generators at the end of
2008.
A copy of the new rate schedules,
as well as other information about the facility, maybe accessed on the
South Carolina Energy Office’s LLRW Disposal Program Web Page at http://www.state.sc.us/energy/llrwdisposal.htm.
Envirocare of Utah’s
Class B and C license application is currently undergoing its technical
review by the Utah Division of Radiation Control. The duration of
the technical review will depend on how quickly Envirocare responds to
the 56 question interrogatory. Answers to 22 of the questions have
been submitted. After the technical review is completed an approval
will be needed by the State’s legislature and governor. The next
meeting of the Utah legislature will be in January 2001.
The Commission maintains a mailing list of individuals and organizations interested in Commission activities. Commission meetings are open to the public and meeting announcements, materials, Annual Reports are distributed to interested persons and groups. The Commission’s office responds to various requests for information that are received.
The Commission has a variety of Fact Sheets, brochures, position papers, and other information available, including project-specific brochures.
The Commission’s web page
became operational in late 1996. Items contained on the Commission’s
web page are newsletter articles, Annual Reports, minutes of Commission
meetings, notices of meetings, legal summaries and other appropriate information.
The web site may be accessed at http://www.cillrwcc.org.
During the past several years
the Commission has been in litigation many times, and has been successful
in defending its legal position. Most recent and current litigation is
summarized below. Visit our web site (www.cillrwcc.org) for details of
past litigation.
State of Nebraska v. Central
Interstate Low-Level Radioactive Waste Commission
(United StatesDistrict Court
for the District of Nebraska, Case No. 4:CV963438).
The Central Interstate Low-Level Radioactive Waste Commission at a meeting on September 30, 1996, passed resolutions after receiving evidence calling for the State of Nebraska to issue its initial draft decision and documents on the license application no later than January 14, 1997, and also calling for a consolidation of the hearing process after the draft decision. The State of Nebraska sued the Commission, claiming that it was entitled to a federal declaratory judgment that the Commission lacks authority to set any schedule for the remainder of the license application review currently underway in the Departments, and that even if it had such authority, the dates set were unreasonable.
Major generators Wolf Creek and Entergy were allowed by the Court to intervene, over Nebraska’s objection. Trial was held before Judge Urbom during July, 1998. The parties submitted written closing arguments and briefed some issues at Judge Urbom’s request. On October 15, 1998, Judge Urbom entered judgment in favor of the Commission. His 18-page opinion held that the Commission had the authority to pass its September 30 motion imposing a decision deadline, and that the deadline contained in the motion was reasonable. Nebraska appealed this decision to the Eighth Circuit Court of Appeals.
On August 16, 1999, the Eighth
Circuit filed an opinion affirming the judgment entered by Judge Urbom.
The Eighth Circuit determined that the Commission had authority to pass
the deadline. The Court decided that the issue of the reasonableness of
the deadline was moot, because the State had made a license decision after
the lower court judgment was entered but before the appeal was decided.
However, in a footnote the Eighth Circuit said, “Without addressing the
issue directly, we believe, in any event, that the deadline established
by the Commission was responsible.” The State did not try to take
the case to the U.S. Supreme Court, so this matter is now completed.
State of Nebraska v. Central
Interstate Low-Level Radioactive Waste Commission
(United States District
Court for the District of Nebraska, Case No. 4:CV973267).
In June and July, 1997, the
Commission approved waste export applications made by a number of Major
Generators. Nebraska’s Commissioner voted “No” on each application,
contending that Art. IV(m)(6) of the Compact gives the Host State veto
authority over all export of waste from the region. On advice of
counsel, the Commission determined that Nebraska’s claimed “Veto” authority
did not apply to the export applications before it, and approved the applications
on a
4-1 vote.
In mid-August, 1997, Nebraska
sued the Commission, seeking a declaration that the export permits issued
by the Commission in June are invalid and that the affirmative vote of
the Nebraska Commissioner is required before the Commission can authorize
any export of waste from the region. Although the Commission took
no action regarding importation of waste to the region, Nebraska’s suit
seeks a declaration that the affirmative vote of Nebraska’s Commissioner
is required before the
Commission can authorize
importation of any waste into the region. On September 13, 1997,
Nebraska amended its complaint to include the export applications approved
by the Commission in July, 1997.
The Commission asked that the case be dismissed unless the waste exporters whose applications were challenged by Nebraska’s Commissioner were made parties. The Court rejected that motion, and the Commission answered the complaint. A short trial was held on October 2, 1998.
On November 23, 1998, Judge
Kopf issued a Memorandum and Judgment in favor of the Commission.
The opinion holds that Nebraska does not have veto power over export applications,
and refuses to decide issues related to future import issues. On
December 8, 1998, Nebraska filed a motion for new trial, which was overruled
and Nebraska has appealed to the Eighth Circuit Court of Appeals. On April
4, 2000, the appellate court affirmed the entire ruling and the case is
now completed.
U.S. Ecology, Inc., and
Central Interstate Low-Level Radioactive Waste Commission, Contested Case
Proceeding over License Denial
(Departments of Environmental
Quality and Health and Human Services of Nebraska)
After the two departments
announced their denial of a license on December 18, 1998, US Ecology filed
a contested case proceeding before the two departments, and the Commission
intervened as an interested party, with both US Ecology and the Commission
seeking a reversal of the license denial. The attorneys for the two
departments, however, then filed an answer in which they said that the
issues of political influence over the license decision could not be decided
in this proceeding for “lack of subject matter jurisdiction.” A preliminary
hearing was held before the hearing examiner, former Nebraska Chief Justice
C. Thomas White, at which point the
Commission announced that
the major generators and the Commission would be seeking to enjoin any
further proceedings in the contested case hearing because of the limitations
being placed on it by the departments. Subsequently, in the lawsuit
filed by the major generators and the Commission against the State of Nebraska
and others, which is described in the following paragraph in this memorandum,
United States District Judge Richard Kopf entered first a temporary restraining
order and then a preliminary injunction against the contested case proceedings
going any further. That preliminary injunction was entered on April
16, 1999. It both halted the contested case hearing and also prevented
the State of Nebraska from billing the Commission, US Ecology, or
the major generators in any way for the legal costs involved in the contested
case proceeding or in the costs of the federal lawt itself. Therefore,
at least until trial of the federal case, now expected in 2002, there will
be no further action in the contested case proceeding. The State
appealed the preliminary injunction, but it was sustained by the U.S. Court
of Appeals for the Eighth Circuit on April 12, 2000. The State did
not then seek to take the issue to the U.S. Supreme Court.
Entergy Arkansas, Inc.
[and all other major generators except NPPD] and Central Interstate Low-Level
Radioactive Waste Commission and US Ecology v. State of Nebraska [and several
individual defendants]
(United States District
Court for the District of Nebraska,Case No.: 4:98CV3411)
In this case, which was filed by the major generators in late December, 1998, the claim was made by those original plaintiffs against the State of Nebraska, the directors of the Departments of Health and Human Services and Environmental Quality, and against the program director for the low-level radioactive waste program, Jay Ringenberg, and others, that the licensing proceeding was politically influenced and the denial was invalid. The plaintiffs also named the Central Interstate Low-Level Radioactive Waste Commission as a defendant, subject to realignment by the court since the Commission’s position was much more likely to be aligned with the plaintiffs than the defendants. The claims by the generators were that the State of Nebraska, under color of state law, had denied the civil rights of the plaintiff generators in various respects, and also that the plaintiff generators were essentially intended beneficiaries of the compact between the states, and that bad faith on the part of the State of Nebraska had caused them tremendous damages.
Shortly thereafter, the Commission,
at its January 1999 meeting, authorized its outside counsel to ask the
Court to realign it as a plaintiff and essentially join in the claims originally
made by the major generators. That has been done, and the Commission,
in its own claim against the State of Nebraska, contended that Nebraska
had operated in bad faith in violation of the compact which is both a federal
law and has the characteristics of a contract between parties. A
temporary injunction was obtained by the plaintiffs preventing any of the
defendant parties from destroying any documents, and that has been communicated
to all the State officials involved.
The plaintiffs, including
the Commission, then moved for a temporary restraining order and then a
preliminary injunction against the State of Nebraska and the other defendants,
prohibiting them from continuing with the contested case proceeding, and
also prohibiting them from trying to charge the costs of any aspect of
the low-level radioactive waste actties against the plaintiffs. The
allegation was that more than $75 million had been spent on the project
by the original plaintiffs in this action (not counting the additional
$20 million or so spent by NPPD which has not joined in the case), and
that allowing the State to continue charging everything to the plaintiffs
was simply a continuation of the bad faith and illegality of Nebraska’s
approach to its role as the host state. The Commission joined in
all those motions for injunctive relief.
On April 16, 1999, United
States District Judge Richard Kopf granted the preliminary injunction,
making extensive findings of probable bad faith by Nebraska in a 38-page
opinion. The requirements for preliminary injunctive relief include
a finding of probable ultimate liability, and the Court therefore was obliged
to make that call and found very substantial and itemized evidence of various
bad faith and political influence on the licensing proceeding. The
State has appealed the preliminary injunction; the Commission and the State
have filed their opening briefs, oral argument was held, and on April
12, 2000 the United States Court of Appeals affirmed Judge Kopf’s decision
in its entirety. The defendants, including the State of Nebraska,
also had filed a motion with Judge Kopf on similar arguments to dismiss
the lawsuit, largely on the baisis of Nebraska’s claim of sovereign immunity
against any such relief as the Court might grant. Judge Kopf overruled
the motion, and this decision was also appealed to the Eighth Circuit.
It will be argued in October, 2000. Assuming the Eighth Circuit rules
similarly to it s April, 2000 ruling, it may be expected that the appeal
by Nebraska will fail. One issue in this appeal concerns whether
Nebraska might have an immunity defense as to the money damages claim against
it, even if it does not have immunity as to all the rest of the case.
The Eighth Circuit may or may not decide that issue. After the Eighth
Circuit decides this second appeal of Nebraska, unless the losing party
persuades the U.S. Supremem Court to consider the issues, the case will
be remanded to the Nebraska U.S. District Court for further proceedings,
including discovery and trial. The State has so far resisted all
efforts to do discovery by taking the two appeals, so the
overall schedule will be
reset when the case returns to the U.S. District Court. That should
be in early 2001.
Now, it would appear trial
is likely in 2002, after the discovery is completed.
The annual Billings Review
of license application work performed by USE was not performed for this
reporting period due to the suspension of project activities. The
project was “moth balled” till further notice due to the license denial
decision of the State of Nebraska in December 1998 and the resulting lawsuits.
Rebate Funds (held in certificate of deposits)
Rebate funds can only be spent to:Commission’s rebate funds not obligated (CIC Acct) $229,461 Principal
1. establish low-level radioactive waste disposal facilities;
2. mitigate the impact of low-level radioactive waste disposal facilities on host state;3. regulate low-level radioactive waste disposal facilities; or
4. ensure the decommissioning, closure, and care during the period of institutional control of low-level radioactive waste disposal facilities.
Must annually report the
expenditures to the Department of Energy.
The Commission does not
have to report to DOE the use or expenditure
of the interest the CIC
earns on the rebate funds.
Commission’s “Guaranty Fund”
rebate case setlement
$600,000 Principal
funds obligated (CIC Acct)
Commission’s $600K in Guaranty
Fund is for the sole purpose of
guaranteeing timely payment
to the state for licensing costs billed to
US Ecology; and must annually
report the expenditures to the
Department of Energy.
$829,461Total Principal
Major Generator money in
the “Guaranty Fund” is $400,000
and the Commission is the
custodian of the funds for the sole
purpose of guaranteeing
timely payments to the state for
licensing costs billed to
US Ecology.
The Commissioners voted at
their June 28, 2000 meeting to
return $300,000 to the major
generators.
Commission Expense Report and Budget for Fiscal Year 2000-2001
| Expense | FY97-98 | FY98-99 | FY99-00 Budget (1) | FY99-00 Actual | FY00-01 Budget |
| Salaries & Benefits | 244,819 | 147,475 | 72,331 | 69,796 | 74,776 |
| Rent | 35,380 | 33,187 | 29,000 | 27,773 | 29,000 |
| Telephone | 9,494 | 6,279 | 6,000 | 5,328 | 6,000 |
| Postage | 3,777 | 2,385 | 1,800 | 1,189 | 2,000 |
| Copy & Printing | 728 | 570 | 600 | 130 | 500 |
| Machine Lease & Maintenance | 7,479 | 8,565 | 5,500 | 4,990 | 5,000 |
| Meeting Transcriptions | 3,348 | 3,645 | 4,000 | 1,826 | 4,000 |
| Dues & Subscriptions | 544 | 312 | 300 | 277 | 1,000 |
| Office Equipment & Supplies | 7,988 | 3,334 | 5,000 | 4,202 | 5,000 |
| Travel & Meeting Expense | 19,701 | 11,063 | 10,000 | 9,252 | 11,000 |
| Insurance | 3,916 | 3,578 | 4,000 | 3,982 | 4,000 |
| Accounting | 27,160 | 27,906 | 36,700 | 36,671 | 25,000 |
| Legal Fees | 205,046 | 302,761 | 311,000 | 277,550 | 300,000 |
| Miscellaneous | 43 | 68 | 500 | 0 | 500 |
| Project Manager | 178,194 | 42,275 | 23,000 | 22,800 | 0 |
| Cash Reserve | 0 | 0 | 0 | 0 | 23,000 |
| Butte Site Maintenance | 25,380 | 17,388 | 34,000 | ||
| Total | 747,617 | 596,403 | 535,111 | 483,154 | 524,776 |
| (1) Amended April 12, 2000 | - | - | - | - | - |
CENTRAL INTERSTATE LOW-LEVEL
RADIOACTIVE WASTE COMMISSION
Financial Statements
June 30, 2000 and 1999
(With Independent Auditors’ Report Thereon)
KPMG LLP
233 South 13th Street
Suite 1600
Lincoln, NE 68508-2041
The Commissioners
Central Interstate Low-Level
Radioactive Waste Commission:
We have audited the accompanying balance sheets of the Central Interstate Low-Level Radioactive Waste Commission (Commission) as of June 30, 2000 and 1999, and the related statements of revenues, expenses and retained earnings and cash flows for the years then ended. These financial statements are the responsibility of the Commission’s management. Our responsibility is to express an opinion on these financial statements based on our audits.
We conducted our audits in
accordance with auditing standards generally accepted in the United States
of American and the standards applicable to financial audits contained
in Government Auditing Standards issued by the Comptroller General of the
United States. Those standards require that we plan and perform the audit
to obtain reasonable assurance about whether the financial statements are
free of material misstatement. An audit includes examining, on a test basis,
evidence supporting the amounts and disclosures in the financial statements.
An audit also includes assessing the accounting
principles used and significant
estimates made by management, as well as evaluating the overall financial
statement presentation. We believe that our audits provide a reasonable
basis for our opinion.
In our opinion, the financial statements referred to above present fairly, in all material respects, the financial position of the Central Interstate Low-Level Radioactive Waste Commission as of June 30, 2000 and 1999, and the results of its operations and its cash flows for the years then ended in conformity with accounting principles generally accepted in the United States of America.
In accordance with Government Auditing Standards, we have also issued our report dated July 21, 2000 on our consideration of the Commission’s internal control over financial reporting and our tests of its compliance with certain provisions of laws, regulations, contracts and grants. That report is an integral part of an integral part of an audit performed in accordance with Government Auditing Standards and should be read in conjunction with this report in considering the results of our audit.
July 21, 2000
KPMG LLP

Notes to Financial Statements
(1) Organization
The Central Interstate Low-Level Radioactive Waste Commission (Commission) was established in 1984 by an interstate compact among the states of Arkansas, Kansas, Louisiana, Nebraska and Oklahoma with consent of Congress through the Omnibus Low-Level Radioactive Waste Interstate Compact Consent Act. The purpose of the Commission is to carry out the mandate of the Central Interstate Low-Level Radioactive Waste Compact by providing for and encouraging the safe and economical management of low-level radioactive wastes within the compact region. The Commission is an instrumentality of the compact member states and as such, is exempt from Federal and state income taxes under Section 115 of the Internal Revenue Code.
(2) Summary of Significant Accounting Policies
Basis of Accounting
The accompanying financial statements are prepared on the accrual basis and reflect assets and liabilities owned by the Commission and the results of the Commission’s operations.
The Commission applies all applicable Financial Accounting Standards Board Statements and Interpretations, Accounting Principles Board Opinions, and Accounting Research Bulletins except for those that conflict with or contradict Government Accounting Standards Board’s (GASB) pronouncements.
Revenue Recognition
a)
Funding from Major Generators
The major generators provide
funding for the siting, licensing, development and construction of the
facility. Revenues are recognized as expenses are incurred. Constuction
and development of the project is currently on hold (see note 6). Therefore,
the Commission did not receive funding from the major generators for the
year ended June 30, 2000.
b)
Export Application Fees
Fees for approval to export
waste are recorded as revenue when earned.
Property and Equipment
Property and equipment consists of furniture, fixtures and equipment recorded at cost. Depreciation is calculated on a straight-line basis over the estimated useful lives of the assets which is currently three to five years.
Restricted Assets
The source of the project fund is from six major generators which are providing funding for the low-level radioactive waste disposal project under an agreement with the Commission (see note 4). The six major generators are Arkansas Power and Light Company, Gulf States Utilities Company, Louisiana Power and Light Company, Nebraska Public Power District, Omaha Public Power District and Wolf Creek Nuclear Operating Corporation. The agreement specifies the project funds provided by the major generators are to be used only to reimburse US Ecology, Inc. (US Ecology) for project costs incurred as defined in Section 4.01 of the Commission’s contract with US Ecology. The use of interest earned on the project fund is not restricted.
Use of the rebate fund is restricted to payment of certain costs incurred to establish the low level waste facility or mitigate the impact of low level radioactive waste disposal facilities on the State of Nebraska.
The Commission has agreed to guarantee payment by US Ecology of certain licensing activity costs incurred by the State of Nebraska. Related to this guarantee, the Commission is obligated to create and maintain a segregated restricted account with a balance of $1,000,000 for a guarantee fund, if needed, for payment of the State of Nebraska’s licensing expenses and payments to its contractors in the license application and review process, should US Ecology default on prelicensing payments to the State of Nebraska. On July 12, 1996, the Commission transferred $600,000 to the guarantee fund from rebate funds. The major generators also deposited $400,000 in the Commission guarantee fund on July 12, 1996. Commission management believes that presently no circumstances exist to cause the use of monies in the guarantee fund for payment of licensing costs incurred by the State of Nebraska. At the end of the prelicensing period, when the license decision is final, the guaranty provisions expire. When that date approaches and any remaining anticipated costs of the licensing activities are determined and paid, the $400,000 deposited in the guarantee fund shall be released to the major generators. The remaining $600,000 may then be used by the Commission for any legal purpose.
The interest income earned on the $400,000 deposited in the guarantee fund by the major generators is remitted directly to the major generators. The interest income earned on the remaining $600,000 is periodically transferred to the rebate fund.
Use of Estimates
Management of the Commission has made a number of estimates and assumptions relating to the reporting of assets and liabilities to prepare these financial statements in conformity with generally accepted accounting principles. Actual results could differ from those estimates.
Reclassification
Certain balances from 1999 have been reclassified to conform with the current year presentation.
(3) Cash and Certificates of Deposit
At June 30, 2000 and 1999,
the Commission had cash and certificates of deposit of $1,917,098 and $1,978,949,
respectively. At June 30, 2000, administrative, community improvement and
project funding accounts included demand deposits of $42,242, which was
covered by FDIC deposit insurance. Also at June 30, 2000, administrative,
community improvement and project funding accounts included $417,865 invested
in short-term federal investment trust accounts backed by the full faith
of the federal government. At June 30, 1999, administrative, community
improvement and project funding accounts included demand deposits of $306,979,
of which $100,000 was covered by FDIC deposit insurance and $206,979 as
uninsured. Also at June 30, 1999, administrative, community
improvement and project
funding accounts included $285,404 invested in short-term federal investment
trust accounts backed by the full faith of the federal government. At June
30, 2000 and 1999, rebate fund certificates of deposit of $100,000 were
covered by FDIC deposit insurance and the remaining $1,340,991 and $1,286,566,
respectively, were collateralized by government ecurities / agencies held
in joint custody at the federal reserve, by the pledging bank, in the Commission’s
name.
(4) Contractual Agreements
The Commission has an agreement with US Ecology for the design, development, construction, operation and eventual decommissioning of a facility for the disposal of low-level radioactive waste. The agreement specifies eight project phases from identification of a host state and preparation of a siting plan to closure and post closure of the facility.
Current funding for the siting, licensing, development and construction of the facility is being provided by six major generators under separate agreement and, in part through equity contributions from US Ecology. Equity contributions were accomplished by US Ecology through credits on billings to the Commission for the facility. The Commission entered into the agreement to provide necessary funding for the project with the major generators.
(5) Lease
Rent expense under an operating lease for office space was $27,773 and $33,187 for the years ended June 30, 2000 and 1999, respectively. The future minimum rental payments are in the amount of $17,046 for the year ended June 30, 2001.
(6) Contingencies
In December 1998, the State of Nebraska denied US Ecology’s license to build and operate the facility. In June 1999, Nebraska passed a law which will withdraw Nebraska from the Compact effective in August 1999. Nebraska would remain a member for up to five years after their notice to withdraw is submitted to the Commission. The Compact has joined in a lawsuit with the major generators against the State of Nebraska for licensing of the site or damages in for a bad-faith denial by Nebraska. The financial impact of these events are uncertain.
(7) Subsequent Events
On July 7, 2000, the Commission reimbursed $300,000 to the major generators for their contribution to the guarantee fund. The Commission replenished the guarantee fund by transferring $300,000 from the rebate fund.
We have audited the financial statements of Central Interstate Low-Level Radioactive Waste Commission (the Commission) as of and for the year ended June 30, 2000 and have issued our report thereon dated July 21, 2000. We conducted our audit in accordance with auditing standards generally accepted in the United States of America and the standards applicable to financial audits contained in Government Auditing Standards issued by the Comptroller General of the United States.
Compliance
As
part of obtaining reasonable assurance about whether the Commission’s financial
statements are free of material misstatement, we performed tests of its
compliance with certain provisions of laws, regulations, contracts and
grants, noncompliance with which could have a direct and material effect
on the determination of financial statement amounts. However, providing
an opinion on compliance with those provisions was not an objective of
our audit and, accordingly, we do not express such an opinion. The results
of our tests disclosed no instances of noncompliance that are required
to be
reported
under Government Auditing Standards.
Internal Control Over Financial Reporting
In
planning and performing our audit, we considered the Commission’s internal
control over financial reporting in order to determine our auditing procedures
for the purpose of expressing our opinion on the financial statements and
not to provide assurance on the internal control over financial reporting.
Our consideration of the internal control over financial reporting would
not necessarily disclose all matters in the internal control over financial
reporting that might be material weaknesses. A material weakness is a condition
in which the design or operation of one or more of the internal control
components
does not reduce to a relatively low level the risk that misstatements in
amounts that would be material in relation to the financial statements
being audited may occur and not be detected within a timely period by employees
in the normal course of performing their assigned functions. We noted no
matters involving the internal control over financial reporting and its
operation that we consider to be material weaknesses.
This report is intended solely for the information and use of the Commissioners, and the Commission management and is not intended to be and should not be used by anyone other than these specified parties.
July
21, 2000
KPMG LLP